Aggressive Expansion: 1.5 GW in 18 Months
Hyper-scale growth has changed the rules of infrastructure delivery … speed is key.
BACKGROUND:
A management consulting group building OFCI / CFCI procurement programs for hyper-scalers globally was tasked with supporting a hyper-scale project that was fast-tracked for 100 MW at ground break and needed to scale rapidly to 1.5 GW in 18 months.

THE CHALLENGE:
- Aggressive expansion from 100 MW to 1.5 GW in 18 months
- Procuring build-to-spec HV and MV Transformers and Circuit Breakers
- Navigating the global supply chain constraints that impact lead times
- Consistent communication across multiple stakeholders
THE SOLUTION:
PDM was initially awarded 25% of the required HV and MV scope. But, from the start, PDM differentiated itself through speed, clarity, and technical support.
PDM ADVANTAGE:
Rather than acting as a transactional vendor, PDM functions as an extension of the customer’s team, helping to navigate the supply chain and design decisions. Within weeks of project kickoff, PDM delivered:
- Complete, on-time, and accurate submittals and drawings
- Transparent, real-time communication
- Application engineering optimization to align design with operational realities
- Proactive coordination to reduce downstream risk
THE RESULTS:
The customer gained more than capacity – they gained a partnership.
- PDM’s scope expanded from 25% to 100%
- PDM established as the primary HV/MV partner
- $40M in orders awarded in 2025
POWERING WHAT’S NEXT:
PDM helps critical power projects stay on schedule, scale with confidence, and get ahead. Contact us to deliver critical power with confidence.