Aggressive Expansion: 1.5 GW in 18 Months 

Hyper-scale growth has changed the rules of infrastructure delivery … speed is key.  

 
BACKGROUND: 

A management consulting group building OFCI / CFCI procurement programs for hyper-scalers globally was tasked with supporting a hyper-scale project that was fast-tracked for 100 MW at ground break and needed to scale rapidly to 1.5 GW in 18 months.

 
THE CHALLENGE:
  • Aggressive expansion from 100 MW to 1.5 GW in 18 months

 

  • Procuring build-to-spec HV and MV Transformers and Circuit Breakers 

 

  • Navigating the global supply chain constraints that impact lead times

 

  • Consistent communication across multiple stakeholders
 
THE SOLUTION:  

PDM was initially awarded 25% of the required HV and MV scope. But, from the start, PDM differentiated itself through speed, clarity, and technical support.

 
PDM ADVANTAGE 

Rather than acting as a transactional vendor, PDM functions as an extension of the customer’s team, helping to navigate the supply chain and design decisions. Within weeks of project kickoff, PDM delivered: 

  • Complete, on-time, and accurate submittals and drawings 
  • Transparent, real-time communication 
  • Application engineering optimization to align design with operational realities
  • Proactive coordination to reduce downstream risk
 
THE RESULTS:

The customer gained more than capacity – they gained a partnership.

  • PDM’s scope expanded from 25% to 100%
  • PDM established as the primary HV/MV partner
  • $40M in orders awarded in 2025

POWERING WHAT’S NEXT:  

PDM helps critical power projects stay on schedule, scale with confidence, and get ahead. Contact us to deliver critical power with confidence.